Zoom
|
| |
Numbers refer to projects listed on the right.
|
| |
Grading, drainging, placing crushed base and bituminous pavement surfacing, sidewalk, curb and gutter, electrical and miscellaneous work on .32 mile of urban route 051 beginning at reference marker 4.9 in the Town of Evanston.
Scheduled Completion: 8/31/10
| Road |
Mileposts |
Delays |
Surface |
| I 80 Bus., US 189 Bus. |
4.29 - 4.61 |
Reduced speeds up to 10 MPH. |
Paved |
Contractor Info
- J Wright Development, LLC
- Riverton, UT
- (801) 302-2200
|
WYDOT Contact
|
Last Update: 4/1/10 11:19 AM
|
Installing new guardrail and upgrading existing guardrail at various locations.
Scheduled Completion: 8/1/10
| Road |
Mileposts |
Delays |
Surface |
| WY 233 |
4.43 - 15.9 |
10 min. delays. |
Paved |
Last Update: 7/13/10 8:03 AM
|
milling plant mix, concrete slab replacement, slab lifting and undersealing and miscellaneous work on 28.10 miles on I-80 beginning at RM 0.00 between Evanston and Bigelow Int.
Scheduled Completion: 9/30/10
| Road |
Mileposts |
Delays |
Surface |
| I 80, US 189 |
0 - 28.1 |
Reduced speeds up to 30 MPH. |
Paved |
Contractor Info
- Interstate Improvement, Inc
- Fairbault, MN
- (507) 333-2677
|
WYDOT Contact
|
Last Update: 5/27/10 8:38 AM
|
|
Maintenance Chip Seal on WY 412 & US 89
Scheduled Completion: 7/27/10
| Road |
Mileposts |
Delays |
Surface |
| US 89 |
87.1 - 94 |
20 min. delays with stopped conditions. |
Paved |
| US 89 |
54.93 - 64 |
20 min. delays with stopped conditions. |
Paved |
| WY 412 |
2.81 - 11 |
20 min. delays with stopped conditions. |
Paved |
Last Update: 7/22/10 3:13 PM
|
|